Let’s break down the two main types of estimates you’ll encounter in construction projects – preliminary and detailed – and why both matter. Think of it like planning a road trip: one’s a rough map, and the other’s the GPS-guided route.

Preliminary Estimates: The "Ballpark Figure"

This is your first guess at costs, done early in a project when details are scarce. It’s like estimating how much a new house might cost based on its size or a similar project you’ve done before.

How it works:

  • Uses historical data (e.g., cost per sq.ft for schools) or parametric models (e.g., ₹X/km for highways).

  • Example: A contractor estimates a 10,000 sq.ft hospital might cost ₹12 crore based on past projects.

When to use it:

  • Feasibility studies (“Is this project even possible?”).

  • Securing initial funding or client approvals.

Pros:

  • Fast and cheap to prepare.

  • Helps avoid wasting time on unviable projects.

Cons:

  • Accuracy can swing ±25-50% (e.g., ₹10-15 crore for that hospital).

Detailed Estimates: The "Exact Blueprint"

This comes after designs are finalized. It’s like itemizing every bolt, beam, and worker hour needed to build a bridge.

How it works:

  • Breaks down every component:

    • Materials: Exact quantities (e.g., 500 tonnes of steel).

    • Labor: Worker days × wage rates (e.g., 50 masons × ₹800/day).

    • Equipment: Crane rentals, fuel costs, etc.

  • Example: A metro station estimate includes ₹2.5 crore for concrete, ₹1.8 crore for steel, and ₹50 lakh for waterproofing.

When to use it:

  • Finalizing contracts and budgets.

  • Bidding for tenders (to avoid underquoting).

Pros:

  • Accuracy within ±5-10%.

  • Minimizes surprises during construction.

Cons:

  • Time-consuming (needs full drawings and specs).

Key Differences at a Glance

Factor

Preliminary Estimate

Detailed Estimate

Stage

Early planning

Post-design phase

Inputs

Rough sketches, past projects

Complete drawings, BOQ, rate schedules

Accuracy

±25-50%

±5-10%

Purpose

Go/no-go decisions

Contracts, procurement, execution

Why Both Matter

  • Start with a preliminary estimate to avoid chasing unrealistic projects.

  • Refine it into a detailed estimate to lock down budgets and prevent cost overruns.

Want to Master Estimation?Bhadanis Quantity Surveying Training Institute offers courses like:

  • Quantity Surveying

  • Estimation & Costing

  • Rate Analysis & BOQ Preparation

  • Tendering & Contracts Management

Learn to create accurate estimates for highways, buildings, and metro projects using Indian standards like IS 1200 and CPWD schedules.

Visit: www.bhadanisrecordedlectures.comCall/WhatsApp: +918603333379

Recent Posts

See All
How to Transition from Site Engineer to Estimator

Ready to move from site engineer to estimator? Discover a step-by-step guide to making the transition, leveraging your field experience and mastering new skills in quantity takeoff, rate analysis, and

 
 
 